Past work
You can see the background, history and planning timeline of the 3rd Precinct building.
Past planning timeline
In 2023, we gathered community feedback on whether we should reestablish the Third Precinct building at Lake & Minnehaha or at an alternative location.
April 2023
Community engagement
We gathered community feedback on whether we should reestablish the 3rd Precinct building at Lake & Minnehaha or at the alternative location.
- We hosted five precinct-wide community meetings.
- We also had eight meetings with cultural communities.
- People also shared their opinions online through the survey.
May 2023 - July 2023
Analyze feedback
- Our consultant team analyzed the community engagement information.
- The team prepared a report and released it in July.
July 2023
Presented community engagement report
On July 18, 2023, we presented the report to the Committee of the Whole.
Sept 2023
Planning for Spring and summer 2024 site cleanup
Site cleanup will proceed in Spring/Summer 2024 at Minnehaha 3000. This is the former 3rd Precinct building location.
The site cleanup will:
- Secure the building
- Improve appearance of the site
- Allow us to remove barriers
Presented Minnehaha 3000 update
On September 19, 2023, we presented the update on Minnehaha 3000 to the Committee of the Whole.
Nov 2023
3rd Precinct building location chosen
- City leadership has voted to build at a chosen Third Precinct building location.
- The location is at 2633 Minnehaha Ave.
December 2023
Presented Minnehaha 3000 update
On December 5 2023, we presented an update to the Committee of the Whole.
Contact us
Minnehaha 3000 Team
Office of Public Service
Address
Public Service Center
250 S. Fourth St.
Minneapolis, MN 55414