17th Ave NE and Northeast River Ridge area

The City will remove part of the asphalt on the streets in these two areas. They will then overlay each street with a new layer of asphalt.

Key information

Dates

Late spring of 2021

Location

17th Ave. NE from University Ave. NE to Monroe St. NE, Northeast River Ridge area, in northeast Minneapolis

Sheridan St. Anthony West

Project overview

In this ongoing street maintenance program, we replace the top layer of asphalt pavement to extend the life of a street between larger reconstructions. The new pavement should last about 10 years.

Other work

There will be some other work done before resurfacing these streets:

  • A minor amount of concrete curb and gutter replacement
  • Some private utility work under the street

Following this work, we will resurface both of the streets.

Timeline

  • Early May 2021: Resurface River Ridge area
  • Mid-May 2021: Replace concrete curb and gutter on 17th Ave. NE.
  • Mid- to late-May: Resurface 17th Ave. NE.

View interactive map

Traffic impacts

Both streets will have short-term closures to through traffic and detours during construction. 

Project phase

This project is complete. 

Input

Design

In Progress

Complete

Contact us

Hazel Wolf

Supervisor Engineering Technician
Public Works

Phone

612-772-2524