53rd Ave. N. resurfacing and bikeway

The City will remove and add a new layer of asphalt and a new bikeway along 53rd Ave. N. from Penn Ave. N. to the Mississippi River.

Key information

Dates

2021-2022

Location

53rd Ave. N. from Penn Ave. N. to Interstate I-94; in north Minneapolis

Lind-Bohanon Shingle Creek

Project overview

53rd Ave. N. is a shared border street between the City of Minneapolis and the City of Brooklyn Center. We're coordinating work with the City of Brooklyn Center over the next two years. We'll finish the work in 2022.

This project is part of an ongoing street maintenance program where we replace the top layer of asphalt pavement. This extends the life of a street between larger reconstructions. The new pavement should last about 10 years.

New bikeway

We identified this segment of 53rd Ave. N. for a new bikeway based on the All Ages and Abilities Network. This project provides an opportunity to add the new bikeway. 

View interactive map

Work schedule

2021

  • Public outreach for the bikeway installation and street improvements
  • Public Hearing for assessments and Minneapolis tax levy in 2023
  • CenterPoint Energy gas main and service upgrades
  • Installation of ADA Ped Ramps on both sides of 53rd Ave. N.
  • Select curb and gutter improvements
  • Sanitary sewer repairs in both cities
  • Water main lining for Brooklyn Center

2022

  • Brooklyn Center creating design plans for a bidding document
  • Cities creating a Joint Powers Agreement for Brooklyn Center to contract the road improvement work; Minneapolis will reimburse Brooklyn Center for the costs associated with the Minneapolis portion of the work.
  • Adding signs, striping, and images for the bikeway improvements

Project meeting

The project team held a pre-construction meeting on Wednesday May 18, 2022.
 
This meeting was a chance to meet with staff again before the work begins. The team shared information, gave updates and answered questions.
 

Traffic impacts

The road will be closed and detoured to through traffic during asphalt milling and paving in 2022.

Construction work on the project will begin the week of June 6, 2022. The work will take approximately 3-4 weeks to complete with the anticipated completion date for the project by early July. Streets will remain open with flagging operations during construction. Road conditions may change on a daily basis.

Project phase

This project is complete.

Input

Design

In Progress

Complete

Street lined with cars and trees
View of existing street pavement on 53rd Ave. N.