Aldrich and Ontario Ave N resurfacing

The City will remove and add a new layers of asphalt along Aldrich Ave. N. and Ontario Ave. N.

Key information

Dates

2021

Location

Aldrich Ave. N. and Ontario Ave. N., in downtown Minneapolis

Lowry Hill

Project overview

In this ongoing street maintenance program, we replace the top layer of asphalt pavement to extend the life of a street between larger reconstructions. The new pavement should last about 10 years.

Schedule

Construction was completed on the following dates:

  • Concrete curb and gutter replacement the week of July 12
  • Milling on Friday, July 23
  • Paving on Monday, July 26

View interactive map

Traffic impacts

The road will be closed and detoured to through traffic during asphalt milling and paving.

Project phase

This project is complete.