Beard Ave. S. sanitary sewer improvement
The City will complete sanitary sewer work on Beard Ave. S. from 51st St to 52nd St W.
Project overview
The City will repair the sanitary sewer at Beard Ave. S. between 51st St. W and 52nd St W, which was first installed in 1930. This will involve replacing manholes. The project will also replace 130 feet of 9-inch clay pipe with 10-inch clay pipe. The repairs will improve sanitary flow and reduce the necessary cleaning frequency.
Traffic impacts
We expect there to be a minimal impact on traffic.
The following temporary traffic impacts may occur:
- Detours
- Lane restrictions
- Intersection reductions
- Parking restrictions
- Revised pedestrian and bicycle routes
Residents, businesses and visitors may experience:
- Noise
- Vibration
- Dust in work areas
You’ll be able to access property throughout construction.
Project phase
This project is complete.