Humboldt Ave S sewer replacement
East Isles Sewer Improvements project
Project overview
We'll replace 535 feet of the existing storm sewer pipe with a larger diameter pipe to better convey stormwater from the area.
We'll also add inlets to:
- reduce flooding at the low point of the street
To fit the larger storm pipe, we'll:
- shift 555 feet of watermain to the west
- replace 405 feet of the 114-year old sanitary sewer with new pipe
Our work will be part of a larger project that the Metropolitan Council manages:
The East Isles Sewer Improvements project will construct sanitary force mains between The Mall and W. 27th St. Timing the two projects together will reduce impact to area residents.
Traffic impacts
During storm sewer project construction between The Mall and W. 27th St:
- Humboldt Ave will be closed to through traffic and only open to local traffic
- Part of the road within The Mall will also be closed.
- Traffic will be detoured around the construction area.
The Midtown Greenway will remain open with a short bypass around the construction.
Other roads may be closed and detoured as the Metropolitan Council completes the rest of their sanitary force main project.
For more details on traffic impacts:
See the Metropolitan Council's East Isles Sewer Improvement project page
Project phase
This project is complete.
Input
Design
In Progress
Complete
Contact us
Lisa Goddard
Senior Professional Engineer
Surface Water & Sewer
Public Works
Phone
Kristi Halicki
Professional Engineer
Surface Water & Sewers
Public Works
Phone