Near North Central area ADA pedestrian ramp upgrades and resurfacing
Dates
2023 - 2024
Location
Area bounded by Knox Ave North, Plymouth Ave N, Aldrich Ave N, 15th Ave N., and 16th Ave N Near-NorthProject overview
This project is part of the ongoing street maintenance program
ADA pedestrian ramp upgrades
The City upgraded pedestrian ramps to current Americans with Disabilities (ADA) standards. This work was completed in 2023.
Resurfacing
City staff will resurface the streets in this area in 2024. We replace the top layer of asphalt pavement to extend the life of a street. The new pavement should last at least 10 years.
View the Near North Central area ADA Pedestrian Ramp Upgrades and Resurfacing Documents
CenterPoint Energy
CenterPoint Energy will be performing work ahead of the pavement resurfacing. For details and updates see their project website.
Read more at the CenterPoint Energy, Minneapolis - Near North Central website
Schedule
Project schedule:
- Select curb and gutter replacement work begins week of June 3rd, 2024.
Project phase
This project is in process