Park Lane reconstruction

The City repaved Park Lane in the lakes area of South Minneapolis.

Key information

Dates

2023

Location

Park Lane off of Burnham Rd.

Cedar-Isles-Dean

Project overview

The project consists of reconstructing 0.3 miles of Park Lane.
 
· Full removal of the existing roadway
 
· New pavement
 
· Curb and gutter
 
· Streetscape enhancements
 
· Green infrastructure
 
· Utility improvements
 
· New signage and pavement markings

 

View the project design layout

View interactive map

Project activity

Project construction update

The Park Lane Reconstruction project is substantially complete. A Grand Opening and ribbon cutting celebration of Park Lane was held on November 8th. 

 

Weekly stakeholders meeting

With the Park Lane project substantially complete, we will be canceling the future stakeholder meetings. Please reach out with any questions to the project team via email.  

Previous meetings

Park Lane reconstruction stakeholders meeting - June 22, 2023

  • A virtual pre-construction meeting was held to get an overview of the upcoming construction work and answer project questions.

Watch the Park Lane reconstruction meeting presentation

 

Project phase

This project is complete.

Input

Design

In Progress

Complete

Contact us

Kyle Wallace

Construction Management Coordinator

Public Works

Blake Conrad

Project Chief

Field Inspector

Phone

952-540-4866